Duration activity
In the Open Standard
Forum GuestMember for 17 years 8 months
- Created
- 1
- 4
0
I create an activity and set duration to 1 day. I then create a resource and assign it to the activity. When I look at the "Resource usage"-view the work has spread out over two days, with 7 hours on one day and 1 hour the next. If I try to adjust the hours so that all 8 hours are in the same day, that day is marked as overtime and the resource percentage has been adjusted to 114% in the Gant-view. I use a resources pool and the time is set from 8.00 to 12.00 and from 13.30 to 17.30, 8 hours a day. I notice activity starts at 9 and not at 8.
What am I doing wrong?
What am I doing wrong?
1 reply
Oldest firstLog in or join to reply