Hannes de BruyneMember for 21 years 2 months
Created
4
3
0
Hello,

can somebody tell me how I can change my time-unit for successors from minutes to days ?

Thank you

Hannes de Bruyne

4 replies

Oldest first
  1. 0
    Zhang Haixiang ·
    Pls give more information ,

    time-unit for successors for duration or lag?
  2. 0
    Zhang Haixiang ·
    MSP always use minute as planning unit.
    But it can show it as day/week/month based on you setting & input
  3. 0
    Hannes de Bruyne ·
    Hello,

    here some more information: I’m looking for the setting how to show the LAG in days.

    Thanks Hannes
  4. 0
    Zhang Haixiang ·
    By defult Lag /duration is shown in day

    Check ’tools’-->’Options’--> ’Schedule’ tab --> ’Duration is entered in’ you can select min/day/week...

    When you type in Lag, you can use:

    "2d" or " 2day" or "2days" ---- 2 days
    "2ed" or "2eday" or "2edays" ---- 2 elapsed day
    "2m" or "2min" or "2minute" ---- 2 minutes
    you can try week month year...