FF and SS Links
In the Open Standard
Susiri LeelaratnaMember for 21 years 8 months
- Created
- 9
- 5
0
I am using MSP Standard 2002. I have encountered the following problems with SS and FF links:
a. Finish to Finish Link: Predecessor’s calendar is transferred to the Successor.
b. Start to Start Link: When an activity has got only a "successive Start to Start Link", as soon as "Actual start" (or % complete) is entered it becomes an open end activity. (Total float calculates up to the project end date)
Can anyone explain/ help as how to resolve?
Regards
Viraja Leelaratna
a. Finish to Finish Link: Predecessor’s calendar is transferred to the Successor.
b. Start to Start Link: When an activity has got only a "successive Start to Start Link", as soon as "Actual start" (or % complete) is entered it becomes an open end activity. (Total float calculates up to the project end date)
Can anyone explain/ help as how to resolve?
Regards
Viraja Leelaratna
9 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?