Alter of Excel cell

Hady Shendy, PMPMember for 20 years 5 months
Created
3
31
0
Hi All
in excel if I need to custom a cell as a duration value
like if I have a cell for "Period for recovery of investment money" value = 11.16 year
how I convert this figure to year:month:day (i.e. 11y:2m:15d)

3 replies

Oldest first
  1. 0
    Svein Myklebust ·
    Why do you need this?

    Excels calcualtions on time ar based on days.
    Why can’t you just use days?

    Svein
  2. 0
    Zhang Haixiang ·
    you need some formula,
    cell A1 = 11.6 then

    year: int(a1)
    month: int(mod(a1*365,365)/30)
    day:: int(mod(a1*365,30))

    you can input the following formula in Cell B1

    =int(a1)&"y:"&int(mod(a1*365,365)/30)&"m:"&int(mod(a1*365,30))&"d"

    But the result is not 100% acurate, as the caculation is based on 365days/year and 30days/month. Only when you have the start date and finish date then you can get the acurate result
  3. 0
    Hady Shendy, PMP ·
    Many Thanks zhang
    keep in tuch