Should splitting tasks increase duration ?
In the Open Standard
Vinod RaturiMember for 20 years 2 months
- Created
- 4
- 3
0
Hi ,
As per the definition given for ’Duration ’. It is active time required to accomplish the task.
But suppose i know , that active time required is 10 days , and due to some reason i am splitting the task to initially 5 days active time , 20 days idle and then again 5 days active. I find after splitting the task the duartion changes itself to 30 days , even though i am active only for 10 days on job.
i want to be enlightened on this behaviour.
Thanks,
regards,
Vinod R
As per the definition given for ’Duration ’. It is active time required to accomplish the task.
But suppose i know , that active time required is 10 days , and due to some reason i am splitting the task to initially 5 days active time , 20 days idle and then again 5 days active. I find after splitting the task the duartion changes itself to 30 days , even though i am active only for 10 days on job.
i want to be enlightened on this behaviour.
Thanks,
regards,
Vinod R
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?