Should splitting tasks increase duration ?

Vinod RaturiMember for 20 years 2 months
Created
4
3
0
Hi ,

As per the definition given for ’Duration ’. It is active time required to accomplish the task.

But suppose i know , that active time required is 10 days , and due to some reason i am splitting the task to initially 5 days active time , 20 days idle and then again 5 days active. I find after splitting the task the duartion changes itself to 30 days , even though i am active only for 10 days on job.

i want to be enlightened on this behaviour.

Thanks,

regards,

Vinod R

4 replies

Oldest first
  1. 0
    Trevor Rabey ·
    When I try what you are doing, my original duration is preserved, regardless of how many times I split the Task, down to 5 x 1 day splits with one day spaces.

    Your definition, using "active" days is pretty close.

    Splits are pretty much the only exception to the definition of duration as:
    the number of working days, according to the calendar for that task, from the start of the task to the finish of the task.

    Check your calendar for the task.
  2. 0
    James Griffiths ·
    Hi Vinod,

    Your task-type is probably set at "Fixed Duration". Double-click on the task, click "Advanced" tab, change the task-type to either "Fixed Work" or "Fixed Units". This will then display the duration in accordance with how many "activity days". Note, however, that all summary-task durations are set at Fixed Duration, so you cannot change those.

    HTH

    James.
  3. 0
    Vinod Raturi ·
    Hi James ,

    Your presumption about task set at "fixed duration" was correct.

    But what does this behaviour implies , does it mean if i have task whose duration is fixed , i cannot have idle time for that task . Since splitting will negate the definition of task " Duration " ?

    Or is there some other angle to it ?

    thanks,

    regards,

    vinod
  4. 0
    James Griffiths ·
    Hi Vinod,

    Glad you "fixed" the problem he he he.

    The term "Fixed Duration" should be more accurately interpreted as "elapsed duration" - as it spans the entire length of the activity, from start to finish - regardless of any idle-time or task splits. In general, however, he task-types are important when you are applying resources to the activities. A so-called fixed duration task will retain its end-date, even if you work fewer or more hours than planned. It will adjust the remaining hours to spread equally across the remaining duration. In essence, you are correct in that a fixed-duration task assumes no idle time unless you specifically input a split. Once you input a split, you might as well allocate it a fixed-work or fixed- unit attribute.

    The fixed-unit and fixed-work task types have different behavioural characteristics when applying resources and re-scheduling uncompleted work - and knowledge is best gained by doing a few experiments. SO I’ll let you get on with it, as it is virtually impossible to explain it in words.

    Cheers.

    James.