MS-Project export to Excel of timephased data

Peter GlickMember for 19 years 6 months
Created
1
5
0
Hi y’all,

What I need is an Excel output from MS-Project of the cost by month for each task with the ability to include lots of task information

Any ideas how I do this? I can use the Analyze toolbar but it does not include anything about a task apart from the name,

Peter

1 reply

Oldest first
  1. 0
    Zhang Haixiang ·
    Hello,

    you can try the great method of copy and paste.

    Change the view to "task usage"/"resource usage"( I’m not sure of the name, i’m using a chinese version), then copy the left part - task information to excel, then the right part the cost informaiton.

    hope this helps

Log in or join to reply