Calculating % on track
In the Open Standard
Jeff ZMember for 18 years 5 months
- Created
- 2
- 2
0
I am trying to display graphical indicators on each task for whether they are on schedule based on today’s date subtracted from duration remaining compared against % complete. I have everything in place, except that the formula (finish - today) gives total calendar days remaining, and I am looking for total work days remaining, based on the project calendar and/or the resources calendar, which includes holidays and vacation.
Any ideas?
TIA (thanks in advance),
Jeff
Any ideas?
TIA (thanks in advance),
Jeff
2 replies