activity type

Jon WardMember for 18 years 4 months
Created
2
4
0
sorry one other P3 to MS Project question,,
how do i determin the type of task,, at the minute , by default all activities are activities,, how do i create a milestone?
many thanks

2 replies

Oldest first
  1. 0
    Jon Ward ·
    ignore that question,, just answered it myself
  2. 0
    Chee Sean Moo ·
    Just to reply for fun.

    MSP is not allowed to define activities type like P3/P6, the activities will automatically change to milestone when you assign the duration to 0.

    But MSP (compare w/ P3) is allow to create hyperlink within cell value, make use for it, you will found more fun!!! ;)