Exporting to Excel
In the Open Standard
Dave TurnbullMember for 19 years
- Created
- 2
- 2
0
Could anyone help, I am using Project 2007 standalone and would like to export the data contained in the cash flow report to excel so I can plot an S curve against it?
I tried going to save as/excel then working through the wizard but that only lets me export particular columns not the whole report.
In 2003 i used a button that allowed me to export straight into excel with my histrogram info, however I cant seem to find it on 2007.
I tried going to save as/excel then working through the wizard but that only lets me export particular columns not the whole report.
In 2003 i used a button that allowed me to export straight into excel with my histrogram info, however I cant seem to find it on 2007.
2 replies