Activity strech
In the Open Standard
Assaf FMember for 18 years 9 months
- Created
- 2
- 2
0
Hi,
How can I make activity A’s start & finish be dependant on two other activities? (B&C)
B will determine A’s start
C will determine A’s finish.
Both of them at the same time - I’ve tried SS & FF but only FF wound up determining A’s dates and SS had no infuence.
Thanks,
Assaf.
How can I make activity A’s start & finish be dependant on two other activities? (B&C)
B will determine A’s start
C will determine A’s finish.
Both of them at the same time - I’ve tried SS & FF but only FF wound up determining A’s dates and SS had no infuence.
Thanks,
Assaf.