Activity strech

Assaf FMember for 18 years 9 months
Created
2
2
0
Hi,
How can I make activity A’s start & finish be dependant on two other activities? (B&C)
B will determine A’s start
C will determine A’s finish.
Both of them at the same time - I’ve tried SS & FF but only FF wound up determining A’s dates and SS had no infuence.

Thanks,
Assaf.

2 replies

Oldest first
  1. 0
    Trevor Rabey ·
    Your question has already been answered at microsoft.public.project
  2. 0
    Alexandre Faulx-Briole ·
    Assaf,
    SS and FF links do not work to build a hammock activity in MSP; you will have to use copye / special paste instead:
    a) copy B’s start date and paste it with a link to A’s
    b) copy C’s finish date and paste it with a link to A’s
    3) add SS and FF links if you wish, but they are not necessary, they will only make you show the "purely logical" relationships between tasks, I mean they demonstrate relationships to the reader
    Alexandre

Log in or join to reply