AC in Earned Value Analysis
In the Open Standard
Mike RobertsMember for 16 years 7 months
- Created
- 2
- 3
0
Hi there,
Has anyone experienced to input manually Actual Cost (AC) rather than automatically being calculated by MSP to get the earned value reports?
Something really interesting happens! If you input AC manually you will have ACWP (which will be calculated automatically) different with AC. Also in Visual Report it doesn’t show BCWP and BCWS. In other words all these costs are shown to be zero. Just gives ACs. Basically MSP calculates the AC based on the resources hourly rates. Sometimes you may have expended more than the amount work times by hourly rates of each resource.
If anyone has dealt with this problem before please give me some idea.
Thanks!!
Has anyone experienced to input manually Actual Cost (AC) rather than automatically being calculated by MSP to get the earned value reports?
Something really interesting happens! If you input AC manually you will have ACWP (which will be calculated automatically) different with AC. Also in Visual Report it doesn’t show BCWP and BCWS. In other words all these costs are shown to be zero. Just gives ACs. Basically MSP calculates the AC based on the resources hourly rates. Sometimes you may have expended more than the amount work times by hourly rates of each resource.
If anyone has dealt with this problem before please give me some idea.
Thanks!!
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?