hello all
i need your help.
i need to give weight to each activity in the project.
for exmaple here are some activity's i'm dealing with:
1-purchase.=10%
2-Infrastructure installation=30%
3-instrument installation=40%
4-delivery=20%

for each activity i need to  take the percent of the activity that finished  and calculate a diffrent weight in  percentages

how can i do it without exporting the info to excel?

1 reply

Oldest first
  1. 0
    Bo Johnsen ·

    Maybe you can use

    Maybe you can use this:

    Introduce a Number1-column containing your percentages (i.e. 10, 30, 40 and 20). Introduce a Number2-column with a customized field containing the formula: [% complete] * [Number1]/100.

    Maybe you also want to apply a rollup sum for summary groups for the Number2-column to get the overall completion % based on your weigthed percentages.

    Hope this is what you were looking for.

     

    Regards,

    Bo 