Stuart AtkinsonMember for 22 years 9 months
Created
6
2
0
How can I avoid showing total slack as say 10.1 days. In otherwords what is wrong with calendars or durations allocated to tasks for this to happen?

6 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Stuart,
    1. did you put a date constraint on one task?
    2. did you change something in the calendars or calendar options?
    Regards,
    Alexandre
  2. 0
    Brian Ultican ·
    Go into Tools | Options | View and pick a date format that shows the time.

    It is possible that the Finish date of the task in question as a time on it that is not the same as the default end time for the calendar.
  3. 0
    Anoon Iimos ·
    i guess it happens because of using percentage lags..?
  4. 0
    Paul Harris ·
    There are many reasons why this may happen, but displaying the times with the date is the first step to resolving what is happening.

    Then as Brian has indicated check that you default start and finish times are aligned with your calendars.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au

  5. 0
    Stuart Atkinson ·
    Thanks everyone,

    I will investigate these options now.

    Stuart
  6. 0
    Stuart Atkinson ·
    The problem was a number of lags with 1.25 days. Thanks again everyone.