Unifiying External Links
- Created
- 3
- 4
Hi everyone, some time back i posted a theme about how unify diferents files in one file in microsoft project using external links.
Well the external link between activities in different files is the use of the path where the file to link existe, adding the name of the file and the number of the task to link and the kind of links between the activities...an example of this is the like i show following:
C:\URBAPETROL\PDT Repro Project\PDT Repro Total\Compras.mpp\1
or
C:\URBAPETROL\PDT Repro Project\PDT Repro Total\Electrico.mpp\223FC+20 días
But now, i need to group all activities in one only file...ok i can create a new file, create the activities calendar, open the individual project files, copy the activities and paste into the new file created...BUT...in the moment of paste the extrernal links continue be external don't became a local links. well, sound crazy but i hope u understand me...now i have a total of 6500 activities in my project and like average 2 links into each activity so...while exist the external links will be exist "gost" activities that will be over the activity that have the external link if is a predecessor or down if is sucessor.
In my Project i have almost 1500 external links, manually is very hard to make the changes so...someone know how i can automate the process of convert the external links in local links...some know how to make this?...
Thanks
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?