problem with percent complete
In the Open Standard
Kp RaoMember for 15 years 2 months
- Created
- 1
- 4
0
Dear all,
I am using Ms project 2007.Physical percent complete progress bar not showing correctly.And also I want to show progress line based on physical percent complete.is it possible.When I try this progress line showing based on % complete not Physical percent complete.
And also I have problem while using duration per compelte.suppose the site team reports 90% and i update this the finish date changes to some other date.But I want to control finish date and keep 90%.is it possible.
Regards,
kp
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?