Seperating remaining duartion from % complete

James BraghiniMember for 16 years 1 month
Created
1
3
0

 This can be done in P3 or P6 but I am not familair enough with MSP to know how. In MSP, how do you seperate remaining duration from percent complete?

Thanks,

James Braghini

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hello James,you can't do that

    Hello James,

    you can't do that in MSP;

    say you have a 6 day task, 50% complete; MSP calculates actual duration = 3 days, remaining duration = 3 days

    when you enter a 4 days remaining duration because the task will be longer than expected, %complete becomes 43%

    Alexandre