How to compare a task's start variance to overall baseline project duration

Joe PalumboMember for 14 years 3 months
Created
0
3
0

Seems like this should be easy, so maybe I am missing something?

I need to compare an individual task's start variance (I know how to get this as I need it) to the project's OVERALL BASELINE duration.  I do not want to compare to the project's (current) Duration, and I do not want to compare to the individual task's duration - I need the overall project's basline Dur.

In other words, I have a Project Baseline Duration of ~77d and Duration of ~85 and I want to see how Task N's Start Var of 3d compares to the Project Baseline Duration.  In this example, I am looking for 3.90% from 3d/77d, not 3.53% which is 3d/85d.

 

When I started out, I thought this would be simple, but I am stumped.

Any help?

Thanks

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?