Skip to content

How to show actual %complete and planned% complete on MS Project 2013 dashboard report

Zahid IslamMember for 10 years 10 months
Created
0
2
0

Hello All,

Does anyone know how to show planned% complete on the bar graph for the dashboard report (project overview).  The graph shows % complete (actual % complete) but I want to compare the planned% complete and actual% complete on that graph.  Any suggestions?

P.S. The report is being generated with MS Project 2013.

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?