Indicator of ressource assignment

Phil GabMember for 10 years 8 months
Created
2
29
0

Hello all, 

I am new to this forum.

I would like to create in the table of my Gantt Chart an indicator showing if one or more resource is assigned to the task (ie green light if any resource, red if none).

i am trying to use a custom field indicator but it does not work.

Exemple : i am trying to check if the field [Resource name] is Null or not.

Any idea how to do ? 

Thanks.

2 replies

Oldest first
  1. 0
    Tom Boyle ·

    Hi Phil, Maybe you have a

    Hi Phil, Maybe you have a typo in the field name.  This works for me in a custom Flag field: IIf([Resource Names]="","No","Yes").  Then green and red stoplights based on the flag value.

  2. 0
    Phil Gab ·

    Hi Tom, I figured it out

    Hi Tom, 

    I figured it out yesterday.

    IIf([Noms ressources]<>"";Oui;Non)

    It works well, i do not know what i have done before ...

    Thanks !