Hi,

I have assigned manhours in the work column but the activity durations keep changing when I change the manhr value, how can I avoid changing activity duration?

3 replies

Oldest first
  1. 0
    Tom Boyle ·

    Raf,Change the Task type from

    Raf,

    Change the Task type from Fixed Units (the default) to Fixed Duration.

    Good luck, tom

  2. 0
    Raf Many ·

    ThanksOne more question;when

    Thanks

    One more question;

    when I change the activity duration the manhrs assigned change automatically, how can I avoid this?

  3. 0
    Philip Day ·

    Hi Raf, There is an

    Hi Raf,

     

    There is an unbreakable link in Automatically Scheduled tasks. So if you change any of these parameters after you have initially created the Task, it will affect the others.

     

    If you change the Task Type to: Manually Scheduled. Make the Required changes and then remember to change back to Automatically Scheduled, you should find that you were able to change just the field expected, without breaking anything else.

     

    Did this solve your problem?

    Kind regards,

    Phil