Adding a weighted % Complete
In the Open Standard
Emma LangMember for 10 years 2 months
- Created
- 0
- 4
0
Is it possible to create a weighted % complete column in MSP?
I have to put a weighted % against different disciplines within the schedule however I'm not really sure where to start.
So I have for example:
Engineering 10%
Procurement 10%
Structural 25%
And so on.
I was thinking I would need to create a text column indicating which discipline each activity comes under and then do a sumif on the durations?
Any help would be appreciated
Thanks
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?