Adding part-time worker extends the duration?
In the Open Standard
Forum GuestMember for 17 years 8 months
- Created
- 7
- 4
0
Hi,
I’ve got a problem with MS Project 2000. When I add a resource (part-time) to a task the duration increases (there are other full-time resources working on the task already).
I made the resources part-time like this:
Resource information window, work-time panel. Marked the non-working days in the calendar.
I can’t use the resource availability in general panel, because on some cases the availability changes during the assigned task and I can give only one effort percentage per task. So the calendar would be good way to do this, but it does not work.
It looks as if the whole team that is assigned to that task starts to use the new calendar? Does someone know how to do this correctly?
Sami
I’ve got a problem with MS Project 2000. When I add a resource (part-time) to a task the duration increases (there are other full-time resources working on the task already).
I made the resources part-time like this:
Resource information window, work-time panel. Marked the non-working days in the calendar.
I can’t use the resource availability in general panel, because on some cases the availability changes during the assigned task and I can give only one effort percentage per task. So the calendar would be good way to do this, but it does not work.
It looks as if the whole team that is assigned to that task starts to use the new calendar? Does someone know how to do this correctly?
Sami
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?