Duration In Days

Yücel CicekciogluMember for 8 years 6 months
Created
2
2
0

Dear All;

 

I am trying to see "Finish Date" - " Actual Start Date" to calculate "how much days i need if my task is late. for example;

 

i planned to complete a task in 10 days, i am in 5 th day of my project and i realized that i need 2 days more to finish this task. so i want to calculate "finish date"- "actual start date"

 

Thanks a lot.

2 replies

Oldest first
  1. 0
    Dhon Bartolome ·

    it is called (Late Finish

    it is called (Late Finish Date) on the Column Tab 

  2. 0
    Susanna Kate ·

    Hi,You said "i am in 5 th day

    Hi,

    You said "i am in 5 th day of my project and i realized that i need 2 days more to finish this task".

    Is it 2 more days in addition to the 5th day (when you realized that) or 2 more days in additon to the 10 days?

Log in or join to reply