Using Import to Update existing schedule
In the Open Standard
Rodney JonesMember for 14 years 4 months
- Created
- 5
- 3
0
Hi All,
I am having trouble with the import to update an existing schedule. I have set the Update criteria for Activities to:
Update Existing and Selected the checkbox to Delete (if not in new schedule).
But the Delete isn't deleting.
V23.12, EPPM runing client version of same on laptop.
Very confused as to why this isn't working.
Rod