Dear All,

We just now bought a P3e software for Project EPC schedule, but we are facing a little bit problem regarding the graphic Report. So far, we were using P3, there was an option in Report Wizard but we can not find it in P3e. Even though we can create directly from print preview but we can not customize the report.

We are looking forward your response to this matter.


Thanks and Regards,

Imron and Rusyidi

2 replies

Oldest first
  1. 0
    Forum Guest ·
    I dont understand what you mean when you say you cant customise the graphical report. What in particular do you want to do?

    Kieran
  2. 0
    Robin Jongen ·
    Report in P3e.

    For graphical report you can use tracking. But you cant customise in the graphical reports like the y-axes accept, if it is in units, to years, months, weeks, days, etc. or no time unit is displayed. If you want to show number of persons, that option is not possible.

    A possibility is to use info-maker (delivered with the cd) or crystal reports) be aware to make sure to install SDK kit of P3e.

    If you go to tabular reports you can change the layout of the report the way you would like.