RE: Project Summarize

Phil PalmerMember for 23 years 5 months
Created
2
3
0
In P3e/c, projects are automatically summarised through the Enterprise Project Structure (EPS). If you require to view project data when the project is closed then you can summaries the data to pre-defined levels of the WBS. Go to the projects window and select the "settings" tab then select the level of WBS the data is to be summarised too. This allows users of Primavision to access summarised data in the Resource and Portfolio tabs.

2 replies

Oldest first
  1. 0
    Tony Banks ·
    Data rolls up to Activity Code level automatically. You just need to open the projects then group by those activity / project codes.
  2. 0
    Forum Guest ·
    But for just reporting at a level 2 from a level 3 or level 4 plan, then this does what you need? Or what is the difference between what p3e/c does and the old summarise option in P3 (except the fact its 1000 times faster!)

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?