import/export xls or dbf-files in p3e/c

Lutz KernMember for 22 years 6 months
Created
8
3
0
High,
where can i find the function to ex-or import files from excel or dbase in p3ec analogue P3? I’d like to ex-or import
e.g.dates in connecting with our procurement control database, activity’s description’s; planned durations and connections and so on...
Who can help me?

Thank you

8 replies

Oldest first
  1. 0
    Mk Tse ·
    I remember you can establish the interface for data exchanage. I forget the application name, you can get it on P3e/c CDs.
  2. 0
    Lutz Kern ·
    thank you very much
  3. 0
    Mk Tse ·
    It is name SDK. I think there is a chapter talking about it in the manual.
  4. 0
    Forum Guest ·
    Just a thought:
    Prepare the program in P3 3.1 (utilizing the import/export option for working in Excel), then, import the P3 3.1 program to P3 Enterprise, any comments, guys.

    PRIMAVERA, ARE YOU LISTENING???????
  5. 0
    Mk Tse ·
    Forum guest, your idea works also. However, you need a licence of P3 3.1 also.
  6. 0
    Forum Guest ·
    Should still work for those who are migrating from P3 3.1 to P3e.

    CHeers guys
  7. 0
    Alex Wong ·
    Dear All

    You can simply use the report functions in the report area

    you can export files in csv or xls format in addition the time distribution data can also export

    However, you need to spend a bit time learn how to use them. only very few people in here (Australia) know how to use them in the most effective ways.

    Alex
  8. 0
    Forum Guest ·
    Hi Alex
    What about importing?

    Cheers

    Zubaidi