Does anyone know how to define/create, (not alter the WBS element) new base methodologies for use with the project Architect.

i.e. say i wanted to replicate a project based upon a standard corporate WBS.

2 replies

Oldest first
  1. 0
    Forum Guest ·
    Project Architect is used to Import a Methodology from Methodology Manager into Project Manager.
    You can either create a project through PA or import a Methodology into an exicting project.

    H.M.PANCHAL
    INDIA
    panchalhm@rediffmail.com
  2. 0
    Jim Fairchild ·
    You can create new base methodologies in Methodology Manager by exporting an existing project in P3e and then importing it into MM. When you import the project you are given a choice on whether to use Actuals or Planned values for the existing project.
    This is actually quite neat because you have a chance to improve your methodologies after they have been used - continuous improvement.

    Jim