Time and Date in Notebook

Richard FuryMember for 22 years 1 month
Created
1
21
0
Is there any way to make the notebook function in Teamplay have an automatic Time and Date stamp?
Thanks in advance!

1 reply

Oldest first
  1. 0
    Shirish Borkar ·
    Hi,

    There is no way you can put the date time stamp automatically. Instead you can write a batch program using SDK & API which will update all (or selected) notebook topics with Date & time stamp.

Log in or join to reply