Jihad DanielMember for 21 years 5 months
Created
2
3
0
After comparing two schedules (baseline & revised),I noticed in the Claim Digger P3e/c report the following:
1- Relationship lags in days are taken in hours (1 day is equivalent to 8 hrs)
2- the General relationship differences are given by relationship Id. instead of activity Id. where change occured. It’s difficult, not to say impossible, to check/filter relationship Id.

Did somebody face the same problems? How did you solve them?

Regards,
J. Daniel

2 replies

Oldest first
  1. 0
    Philip Jonker ·
    On you point 2 I find it hard to believe that a computor can give such a complicated reply. Try and find the guy who wrote it and afterwards eliminate him
  2. 0
    Ronald Winter ·
    J.,

    The alternative is to use Schedule Analyzer. It is far better than Claim Digger and does more. Don’t take my word for it (after all, I am the Developer.) Look at what others have to say about it here or check out the brochure at http://www.ronwinterconsulting.com/sa_brochure.htm.