Issues with Earned Value Labour UNits
In the Open Standard
Ron BeecheyMember for 24 years 4 months
- Created
- 7
- 2
0
I have a problem were an activity is 100% complete the budgetted labour units are 8 the remaining is 0 the actual is 8 yet the earned value labour units is 0. If I understand this correctly the earned is simply the actual or more if the activity went longer than budgetted.
The earned value doesnt seem to populate. Is there a switch I don't have turned on under users or admin or even the project.
UNsure of what is happening.
7 replies