Adding Steps

Jihad DanielMember for 21 years 5 months
Created
2
2
0
This function is important for measuring progress of work but unfortunatly is not performed well in P3e.It will also avoid breaking down activities to a multitude of corresponding tasks and it will give as much as possible a realistic progress % complete that Site Construction could not measure for one general activity.

In past years, we were using excel sheet to calculate the percentage of each broken down activities related to a certain task, then get the required % complete and insert it in P3. As an example, in a construction schedule, concrete work or even each structural work like slab, column, etc. is broken down into Placement of Shutter, Reinforcement and Cast-in-Situ.

In P3e, we can add for each concrete activity the 3 mentioned steps and give them weight factors. The issue is that when we do that, update the steps with actual %, put a start date to the related activity and run it, I noticed the following:
1- Neither physical nor duration % are being calculated automatically.
2- It is not showing the actual start date on any of the steps.

Do you agree with the above or have some comments?

Regards,
J.S. Daniel

2 replies

Oldest first
  1. 0
    Bill McMichael ·
    J.S,

    You need to check two settings.
    1. On the Project screen, calculations tab make sure "Activity Pct based on activity steps" is checked.
    2. For the activity, make sure % compl type is Physical. This is on the status tab of activity form.

    This will compute PCT of activity based on step progress.

    Regards,
    Bill

  2. 0
    Jihad Daniel ·
    Bill,

    Thanks a lot. I forgot to click on the "Activity pct based on activity steps. It is really very useful this step function.

    Regards,
    J.S. Daniel

Log in or join to reply