Adding Steps

Brent HurseyMember for 21 years 6 months
Created
2
2
0
Does anyone know a way of adding at least one step to each activity without having to do it manually or cut and paste? A default function would be nice to add one step that is weighted 100%

Thanks,
Brent

2 replies

Oldest first
  1. 0
    Niek Zonneveld ·
    5.0 will have step templates.

    Furthermore if you copy activities (with steps) you will also copy/paste the steps underneath (works in any >3.X version)

    Hope this helps,

    Niek.
  2. 0
    Brent Hursey ·
    Thank you for your help!