Help.External early start data

Shengyun HeMember for 20 years 6 months
Created
4
3
0
i found that i can not fill the external early start and finish data in Primavera5.0.and i dont know in which case i should use it...why~who can tell me the reason?


Thx & Best Regards

Sandwind He

4 replies

Oldest first
  1. 0
    Dinesh Kumar Damavarapu ·
    Hi,

    What do you mean by external early start and finish.

    Regards

    Dinesh
  2. 0
    Shengyun He ·
    what i trying to say is i can not fill the column of external early start data also the external early finish data. i double kick the blank of this column, it will display a dialog box of calendar,u can choose any day there,but after that,it’s still blank there.it’s seams we can not fill this column by manual work.
    Q1,in which case this column will have a value?(whatever by manual work or by calculated.
    Q2,in which case i have to use this external early star data?
    Q3,how to use it?

    Thx~
    Best Regard~

    Sandwind He
  3. 0
    Jash Sales ·

    Hi Shengyun, External dates

    Hi Shengyun,

    External dates exists only when your activity is link to another activity in different project; therefore, it cannot be filled directly in the column of your current programme. These dates indicates only when your activity is link externally to other project. 

    Regards,

    jacob

  4. 0
    Mike Testro ·

    Hi Jash There is no need to

    Hi Jash

    There is no need to reply to a thread that is more than 5 years old.

    Best regards

    Mike Testro