P3 3.1 Conversion Issues
In the Open Standard
JK MorrisMember for 20 years 5 months
- Created
- 1
- 2
0
Does anyone have tips for P3 3.1 conversion? I have a large project, 9000+ activities, and I am running into an error in the conversion process.
Some data comes over, but none of the durations, activity codes, resource codes, or relationships come over.
Here is the exception report from the conversion utility:
*****************************************************
* EXCEPTION REPORT *
*****************************************************
Date: 25-May-06
Executable: PM.exe
Application: Primavera Project Management
Event Code: VTFRN-3758-6
Message:
TCVirtualTable.FindRowNewIndex: Adding row
(TASKACTV - Activity Code Assignment: 58712, 7188 - .)
conflicts with existing unique key: (7188).
Context:
1: TfrmWizImport.wizImportFinish
2: TfrmWizImport.wizImportBeforeShowPage
3: TfrmWizImport.RunImportWizard
4: TfrmMain.actHomeExecute
5: TfrmMain.actFileImportExecute
6: TCArcturusAssignMgr.InsertPROJWBSRow
7: TfrmMain.actProjectsExecute
8:
9:
10:
Detail:
Type: Exception
Object Type: TCUltraButton
Components
==========
ORI: ORI Win32 #
ORI/DB: PMDB,0500.0024.0001.0002
IMG: IMG Win32 #1000
System Info
===========
Username: ***** Hostname: *****
OS Version: Windows NT ver 5.1, build 2600, Service Pack 2 (Intel Pentium)
Some data comes over, but none of the durations, activity codes, resource codes, or relationships come over.
Here is the exception report from the conversion utility:
*****************************************************
* EXCEPTION REPORT *
*****************************************************
Date: 25-May-06
Executable: PM.exe
Application: Primavera Project Management
Event Code: VTFRN-3758-6
Message:
TCVirtualTable.FindRowNewIndex: Adding row
(TASKACTV - Activity Code Assignment: 58712, 7188 - .)
conflicts with existing unique key: (7188).
Context:
1: TfrmWizImport.wizImportFinish
2: TfrmWizImport.wizImportBeforeShowPage
3: TfrmWizImport.RunImportWizard
4: TfrmMain.actHomeExecute
5: TfrmMain.actFileImportExecute
6: TCArcturusAssignMgr.InsertPROJWBSRow
7: TfrmMain.actProjectsExecute
8:
9:
10:
Detail:
Type: Exception
Object Type: TCUltraButton
Components
==========
ORI: ORI Win32 #
ORI/DB: PMDB,0500.0024.0001.0002
IMG: IMG Win32 #1000
System Info
===========
Username: ***** Hostname: *****
OS Version: Windows NT ver 5.1, build 2600, Service Pack 2 (Intel Pentium)
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?