Project Levelling

Paula WalshMember for 20 years 4 months
Created
1
1
0
When using the leveling tool in Primavera (release 5.0) there is a significant difference in the project end date and activity task start and finish dates when the "preserve schedule early and late dates" option is selected.

How do I know to utilize this option or not, it prolongs the project by 2 months, but when the option is not chosen the project ends earlier. There is not an over allocation of resources that I can see when the option is not selected, but I do not understand what the program is doing differently when the option is selected or not.


Paula

1 reply

Oldest first
  1. 0
    David Kelly ·
    Paula,

    58 views of yout post and no reply!! Couldn’t resist the challenge. Need to know more about what dates you are actually looking at. If you group and sort by Project so that dates role up to the project level, what are Finish, Early Finish and Remaining early Finish, with or without "preserve"

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?