Excel Import
In the Open Standard
Hubert GeierMember for 20 years 2 months
- Created
- 1
- 1
0
I tried to import and Excel file using the latest version of P3e (Version 5). How to set the start or end date via importing? New activities have default duration and are placed at beginn, although start and end date are given.
The help states:
When importing, the planned start date uses the data date as its value if its field is blank (null).
So is there a way to get around this? start_date and end_date get not updated when I reimport and just exported file, where I changed start and end date.
The help states:
When importing, the planned start date uses the data date as its value if its field is blank (null).
So is there a way to get around this? start_date and end_date get not updated when I reimport and just exported file, where I changed start and end date.
1 reply
Oldest firstLog in or join to reply