Overall % Completion

Mirza Imam BaigMember for 23 years 5 months
Created
1
2
0
Hello Friends

Can anyone guide me, in P5, how to show Overall % Complete on the summary level when the % completion type for the activities is Physical completion.

Thanks
Imam Baig

1 reply

Oldest first
  1. 0
    Marcio Sampaio ·
    Go on Assignments. There u can see % Complete by summary for Costs and Units.

    Regards.