EV , Current v Baseline Project - Help
In the Open Standard
Peter HolroydMember for 21 years 4 months
- Created
- 2
- 2
0
If you copy the current project as a baseline, why does P5 not replicate the start / end dates as planned start / finish in the baseline for in progress activities?
What are the 3 settings for Calculating EV in the Admin, Preferences settings for?
What’s the real difference in using them and why does PV change with each setting ?
All I get from Primavera is "check the dates / EV and correct them" - OK for 20 activities but try that on 1,000 ?
What are the 3 settings for Calculating EV in the Admin, Preferences settings for?
What’s the real difference in using them and why does PV change with each setting ?
All I get from Primavera is "check the dates / EV and correct them" - OK for 20 activities but try that on 1,000 ?
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?