Skip to content

EV , Current v Baseline Project - Help

Peter HolroydMember for 21 years 4 months
Created
2
2
0
If you copy the current project as a baseline, why does P5 not replicate the start / end dates as planned start / finish in the baseline for in progress activities?

What are the 3 settings for Calculating EV in the Admin, Preferences settings for?
What’s the real difference in using them and why does PV change with each setting ?

All I get from Primavera is "check the dates / EV and correct them" - OK for 20 activities but try that on 1,000 ?

2 replies

Oldest first
  1. 0
    Steven Oliver ·
    P3e uses the fields Planned Start & Planned Finish as the Baseline Dates. This generaaly works fine except for Completed & In-Progress activities. Use Global Change to set the Planned Start/Finish to current Start/Finish dates.
  2. 0
    Sufian Malik ·
    Peter

    In answer to the settings in admin / admin preferences:


    Section 1
    Based on what i’ve just read, I’m assuming progress on your plan is updated at the activity level so when you you put in your percent complete it calculates the EV.

    In your case you could also use the radio buttons
    1) 0/100 so calculates 0 after activity started and then as 100% after activity calculated
    2) 50/50 - calculated as 50% after actual start and then 100% after actual finish
    3) custom percent complete. user defined percentage like 30% after an actual start and then 100% after actual finish completed

    Section 2
    Depending on which one you use, your estimate to complete will change. By the way if you try them out one by one you can see whats happening for yourself. Suggest you go to the WBS window, click on the Earned Value tab and change each one from there rather than changing the admin preferences.
    performance factor = 1, optimistic result
    performance factor = 1/cpi, most likely result
    perforance factor = 1/(cpi*spi), pessimistic result
    the last one allows you to put in your value


    Section 3
    May be useful for your problem?

    Regards

    Sufian

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?