Shutdown Plan - Help
In the Open Standard
Ian ThomsonMember for 19 years 10 months
- Created
- 1
- 2
0
Guys
I am looking to try & sort out a shutdown plan but am having a problem with the manning.
How can i get P3e to show 10 mechanical techs on days & 4 on nights against 1 activity with a 24 hour calander ??
I can adjust the resources by using the units & prices to show 10 men from 7am to 7pm & 4 men from 7pm to 7am but is this the only way ??
thanks in advance
ian
I am looking to try & sort out a shutdown plan but am having a problem with the manning.
How can i get P3e to show 10 mechanical techs on days & 4 on nights against 1 activity with a 24 hour calander ??
I can adjust the resources by using the units & prices to show 10 men from 7am to 7pm & 4 men from 7pm to 7am but is this the only way ??
thanks in advance
ian
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?