Progressing without Updating

Matthew LovkisMember for 19 years 10 months
Created
3
2
0
Is there any function in P3e which automatically updates the progress of activities solely on where the data date is placed?

For example, if I were to drag the data date two weeks forward could P3e automatically start any activities that fell under that time period. And could it do this without extending any dates.

Cheers,

Matt Lovkis

3 replies

Oldest first
  1. 0
    Karim Mounir ·
    Hi Matthew,

    U can use the "Schedule % complete" to show how much of the activity’s baseline duration has been completed so far (till the data date).

    U can make a copy of the schedule that u work on and assign a baseline to it, then update the schedule as per ur data date and u’ll find the "Schedule % complete".

    HTH.

    Regards,
    Karim
  2. 0
    Rodel Marasigan ·
    Hi Mathew,

    I think you’re referring to Progress Spotlight where you can update your progress against you data date. Any activities highlighted by progress spotlight will be updated automatically without extending dates.

    HTH
    Rodel
  3. 0
    Ruben Quintal ·
    Mathew,

    Run the "update progress" under tools menu, enter the desired date when prompted and then click run.
    Hope this helps.

    BEN