Skip to content

P3e - Project Export without Baseline!!!

Matt RudgeMember for 19 years 7 months
Created
2
2
0
Hi all,

Before going on holiday I exported a project as an XER to a network drive so a colleague could update whilst I was away.

I have returned today to find this was unable to be done as the exported XER file did not contain the Baseline!!!

Has anybody else experienced this? If so how did you get over it (apart from moving to a central database, which we are in the process of doing and will need to move locally stored projects from individuals machines to network when finalised!!)

2 replies

Oldest first
  1. 0
    Arthur Godbeer ·
    That’s how it works in 5.0. Including baseline(s) in one step is an option in 6.0.
  2. 0
    David Forrest ·
    One solution is to restore the baseline to a project, take a copy, reattach original baseline, export project and copy of baseline then re-attach. A bit cumberome but, as previously pointed out, P6 will allow you to export up to 3 baselines attached to your project.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?