P3e - Project Export without Baseline!!!
In the Open Standard
Matt RudgeMember for 19 years 7 months
- Created
- 2
- 2
0
Hi all,
Before going on holiday I exported a project as an XER to a network drive so a colleague could update whilst I was away.
I have returned today to find this was unable to be done as the exported XER file did not contain the Baseline!!!
Has anybody else experienced this? If so how did you get over it (apart from moving to a central database, which we are in the process of doing and will need to move locally stored projects from individuals machines to network when finalised!!)
Before going on holiday I exported a project as an XER to a network drive so a colleague could update whilst I was away.
I have returned today to find this was unable to be done as the exported XER file did not contain the Baseline!!!
Has anybody else experienced this? If so how did you get over it (apart from moving to a central database, which we are in the process of doing and will need to move locally stored projects from individuals machines to network when finalised!!)
2 replies
Oldest firstLog in or join to reply