How to import WBS into P5 from Excel

Maya CMember for 19 years 4 months
Created
7
2
0
IS there a way to import just WBS codes into P5?

I am trying to import a huge project with many WBS codes. When I try to import activities, the import kind of lumps all the activities together and ignores the WBS codes I have in my input (import) file.

However, if I go into P5 and MANUALLY create the WBS and re-import, it recognizes the WBS and imports it correctly.

I am trying to avoid Manually creating WBS since I have so many of them, and I think it is a big waste of time to create it manually.

Any pointers?

Thanks much!

7 replies

Oldest first
  1. 0
    David Kelly ·
    The rule in P5 is explicit and absolute, if a data item CAN come from a pick list, it MUST come from a pick list.

    So the WBS must exist in the project before you import activity data in Excel.

    Two choices.

    Download Dictionary.XLS from the Primavera Support Centre. This uses the SDK to allow dictionaries to be updated.


    Import your spreadsheet into P3, and migrate the P3 project.
  2. 0
    Santosh Bhat ·
    Dictonary.xls doesn’t let you modify the WBS structure for a project - unfortunately.

    Another option, thats rather long winded is to:

    1) Create the WBS using P3 (and its corresponding dictionary.xls file)
    2) Import this into P5 as a flat WBS structure
    3) Manually adjust each flat entry to suit your hierarchy.

  3. 0
    David Kelly ·
    OOOPS,

    Santosh Bhat is right, its our toolkit we use for WBS. The P3 route is the one.
  4. 0
    Andrew Podolny ·
    I’ve used to use Excel macro which takes data from Excel spreadsheet and emulates keystrokes in P5 (through Windows API). Unfortunately it requires some programming skills but it’s worth it.
  5. 0
    Rodel Marasigan ·
    Hi All,

    WBS in P3e/P5 can be import using ODBC connection into PMDB database. For those who are familiar in the structure of PMDB database and using ODBC should not have any problem importing or creating WBS thru SQL or ODBC using PROJWBS table.

    Another way for those who don’t have access to ODBC and not familiar PMDB database I can teach you step by step using Excel spreadsheet to import your WBS but it requires some knowledge on the database structure because P3e/P5 database are using ID code and not name. It also needs a practice to understand how it works but I guarantee you that it works and worth of learning it.

    For those interested send me a PM with your email address so I can send you also the sample file.

    Regards,
    Rodel
  6. 0
    Mauricio Reyes-Quintero ·

    Can you give those steps tp

    Can you give those steps tp create a new wbd in excel and the  export it to primvara P6.

     

    Thanks for your help.

     

    Cheers

  7. 0
    Mimoune Djouallah ·

    Dear Plannershope this

    Dear Planners

    hope this help

    http://www.plannertuts.com/tutorials/how-to-import-wbs-from-excel-to-primavera-p6-using-the-sdk-722/

     

    regards

    mimoune

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?