import P3 to P5
In the Open Standard
Frank NealMember for 23 years 8 months
- Created
- 13
- 1
0
We have recently imported a P3 schedule into P5.
We noticed the start and finish dates to be the same.
The calendars are exactly the same ( P3 & P5)
yet the orig dur in P5 is less than the Orig dur in P3
i.e one task P3 had 26 days ODU and now the same task in P5 has 21 days ODU..
any pointers!!
thks
Frank
We noticed the start and finish dates to be the same.
The calendars are exactly the same ( P3 & P5)
yet the orig dur in P5 is less than the Orig dur in P3
i.e one task P3 had 26 days ODU and now the same task in P5 has 21 days ODU..
any pointers!!
thks
Frank