Adding subcontracts to P3e
In the Open Standard
Al MacLeodMember for 19 years 8 months
- Created
- 2
- 1
0
Hi all,
I have added my man hours as resources (labour) with cost per hours to get the total cost of manhours.
I want to be able to produce a project cost s curve and I now want to add the procurement costs and the subcontracts. What is the general consensus.
Should I add the procurement costs as resources of material type and the subcontracts as resources of non labour type.
or
Should I add both as expenses.
What are the merits and downsides of both options?
Thank you in advance for any comments.
I have added my man hours as resources (labour) with cost per hours to get the total cost of manhours.
I want to be able to produce a project cost s curve and I now want to add the procurement costs and the subcontracts. What is the general consensus.
Should I add the procurement costs as resources of material type and the subcontracts as resources of non labour type.
or
Should I add both as expenses.
What are the merits and downsides of both options?
Thank you in advance for any comments.
2 replies
Oldest firstLog in or join to reply