Adding Baselines

Richard RowberryMember for 23 years 6 months
Created
7
4
0
When trying to Add Baselines in the "Maintain Baselines" Dialogue box, Is there a limit to the number you can have. Looking at one project, it seems that 10 is the limit, but i’m sure i heard somewhere that there wasn’t a limit to how many you can have assigned?

Thanks

Richard

7 replies

Oldest first
  1. 0
    Steven Oliver ·
    Admin, Admin Preferences, Data Limits.

    If you have the necessary priviliges, you can increase the number of baselines there.
  2. 0
    Marcio Sampaio ·
    U can increase it to 50 baselines. But u can only see 3 (first, second and third baseline) on your grantt chart.

    Admin / Admin Preferences / Data Limits / Maximum Baselines per Prpject.

    Regards.
  3. 0
    Richard Rowberry ·
    Thanks Steven/ Marcio,

    I’ll get the necessary priviledges and go from there,

    Regards

    Richard
  4. 0
    Ronald Winter ·
    Actually, in Version 5 you can have as many baselines as you wish. Good luck!
  5. 0
    Marcio Sampaio ·
    Hello Ronald;

    Can i see more then 3 baselines in grantt chart using P5??

    Thanks and Regards;

    Marcio Eduardo.
  6. 0
    Ronald Winter ·
    Not without drinking heavily.
  7. 0
    Marcio Sampaio ·
    Thanks!!