Displaying Calender Days

Brian BeckMember for 19 years 1 month
Created
4
3
0
Has anyone been able to display calander days in P5 when a 5 day work week is designated as the project calander.

4 replies

Oldest first
  1. 0
    Oliver Melling ·
    Brian,

    You can only show original duration and duration.

    You can’t show the elapsed calendar days.

    Also, P5 calculates durations based on the equivalant hours entered spread across the no of ’hours per period’ in the admin preferences, so if you use multiple calendars with different number of hours per period, then the duration columns won’t show the correct duration for all actvities.

    Oliver
  2. 0
    Brian Beck ·
    Thanks for the info. Oliver.

    What I’m trying to do is display calender days under original duration or a similar column. I’m running into some confusion when presenting my schedules that are based on a 5 day 40hr work week. If there is any way to take the overall time from the start date to finish date and display that, that would work.
  3. 0
    Rodel Marasigan ·
    Brian,

    You can use User Defined Fields and update that using Global change or import the data from excel spreadsheets. That will do the trick.

    Regards,
    Rodel
  4. 0
    Oliver Melling ·
    Bri,

    Rodel is right, but is using UDF’s is just a frig, P5 won’t do what you want I’m afraid.

    Whomever you are showing the plan to can just look at start and finish dates to get an idea of the calendar duration.

    Oliver