Skip to content

Acitvity Sequence in WBS

Minhas ShaikhMember for 19 years 6 months
Created
4
3
0
Hi,
I am trying to copy of one WBS including atvities in same project but after past the order of activities is changed. I need those activities in same order.
Can anyoby help me for solving this problem. The are 26 activities in that WBS all are linked.

Thanks
Minhas

4 replies

Oldest first
  1. 0
    Karim Mounir ·
    Hi Minhas,

    Each activity in a schedule has its unique "Activity ID".

    If you want to show the activities in the new WBS sorted as in the old WBS, then u’ve to link the 1st activity in the new WBS with a predecessor in the old WBS (or assign a constarinat date to it) and since the activities in the new WBS are linked then after setting the data date and scheduling the programme the start/finsh dates will be updated, u can sort them by start date (By clicking on the column titled Start).

    HTH

    Regards,
    Karim
  2. 0
    Patricia Le Clainche ·
    Hello Minhas,
    Regarding the order you want after copying, on which column do do sort ? By Activity ID? By Start or Finish Date ?
    If you want to sort by Activity ID, you should be able, just after copying to change Activity ID in order to sort the good way.

    Good luck.
    Patricia

  3. 0
    Niek Zonneveld ·
    Minhas,

    Patricia is right. P5 uses a FIFO buffer, so the order in which you copy is the order in which you paste.

    H.T.H.
  4. 0
    Suresh Sankarankutty PMP ·
    There is no big deal on this issue.Your question is self explanatory that, you are using Acitivity id as sorting field. So nothing to do but just click on the activity id Titile until you see a watermark of a small arrow pointing down.

    Good Luck
    Suresh

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?