Planned Labour Units
In the Open Standard
Jiayin YaoMember for 19 years 6 months
- Created
- 2
- 4
0
Hi All ,
I got the report for cumulative budgeted manhours, calculated based on the baseline .
But when i check the manhours under the column planned labor units , it show the different hours . I assume this number should be the same as the budgted cumulative hrs show in the report . I have already checked the week beginning and ending , they do not match each other at all . How does the P3e calculate the manhours ? Did I miss something ?Please help me . Thank you
Jia yin
I got the report for cumulative budgeted manhours, calculated based on the baseline .
But when i check the manhours under the column planned labor units , it show the different hours . I assume this number should be the same as the budgted cumulative hrs show in the report . I have already checked the week beginning and ending , they do not match each other at all . How does the P3e calculate the manhours ? Did I miss something ?Please help me . Thank you
Jia yin
2 replies
Oldest firstLog in or join to reply