Planned Labour Units

Jiayin YaoMember for 19 years 6 months
Created
2
4
0
Hi All ,

I got the report for cumulative budgeted manhours, calculated based on the baseline .

But when i check the manhours under the column planned labor units , it show the different hours . I assume this number should be the same as the budgted cumulative hrs show in the report . I have already checked the week beginning and ending , they do not match each other at all . How does the P3e calculate the manhours ? Did I miss something ?Please help me . Thank you

Jia yin

2 replies

Oldest first
  1. 0
    Anoon Iimos ·
    check your calendars, i guess differences between resource calendars and activity calendars affect the calculations
  2. 0
    Jiayin Yao ·
    Hi Annon ,

    Thanks for your help. I checked the activities calendar and resources calendar ,they are different. But for the resources calendar I cannot change it , they have been greyed out . I will contact the P5 administrator here. Cheers!!!!