Problem during import the P5 file to P6

Hengxiang ShenMember for 22 years 10 months
Created
8
29
0
When i import the P5 file to P6, the problem happened and the detail information is as following:
*****************************************************
* EXCEPTION REPORT *
*****************************************************
Date: 02-Jan-08
Executable: PM.exe
Application: Primavera Project Management
Event Code: AVAA0-2610-9
Message:
Access violation at address 00E7B064 in module ’PM.exe’.
Read of address 00000000
Context:
1: TfrmWizImport.wizImportFinish
2: TfrmWizImport.wizImportFinish
3: TfrmWizImport.wizImportBeforeShowPage
4: TfrmWizImport.wizImportFinish
5: TfrmWizImport.wizImportBeforeShowPage
6: TfrmWizImport.RunImportWizard
7: TfrmMain.actHomeExecute
8:
9:
10:
Detail:
Type: EAccessViolation
Object Type: TCUltraButton
Components
==========
ORI: ORI Win32 #
ORI/DB: PMDB,0600.0011.0001.0002
IMG: IMG Win32 #1000
System Info
===========
Username: u388793 Hostname: WXP1951L3D2801
OS Version: Windows NT ver 5.1, build 2600, Service Pack 2 (Intel Pentium)

I am using P6 standalone revision, i have send this case to Primavera and still can not get solution. Anyone who has the answer please post.

Thanks,
Shen Hengxiang

8 replies

Oldest first
  1. 0
    K D ·
    Hi.
    In most of the case, this kind of error (AVAA0) is caused by layout corruption. But you’re doing importation, not working in activity view.
    I think it’s a Primavera bug. Perhaps we have to wait for a service pack. :-)
    You can try to reinstall the client module in the meantime.
    Thanks
  2. 0
    Dieter Wambach ·
    Hi Shen Hengxiang
    Did you check if the project was properly imported? Sometimes you receive such error messages due to time-out, corrupt layouts, e.t.c. but with the project everything is ok. Then you just ignore.
    "Read of address 00000000" is strange because no proper value; another hint for a time-out. Primavera is very sensible with this.
    If the XER-file is on a server, you may copy it onto your local PC before the import.
    Did you check the event log of your PC?
    Regards
    Dieter
  3. 0
    F N ·
    Hi,

    This is very interesting. We’ve had kind of the same problem. We’re running Primavera SP3 and when a user pressed F5, he got the following error:

    Type: EAccessViolation
    Event Code: AVAA0-0370-B
    Description: Access violation at address 0066BF5F in module ’PM.exe’. Read of address 00000074.

    Once misleading factor is that when this occurred, we found out that 30 sessions all using the same user ID we’re still up and running. After killing those sessions, the problem was resolved. We tried the F5 function and all was well.

    We’re looking for a clearer explanation to this but can’t seem to find one.

    Anyone can help?

    Thank you
  4. 0
    Dieter Wambach ·
    Hi
    How many persons were using P5? If 30, the it was ok with the sessions, ID = (same) user + session-id, so unique. If not 30 users, then your IT should check the network. Under Admin --> User --> you can add the column "logged in" and see all current users.
    For the event-code you’ll have to contact your local dealer. They have a list for reference.
  5. 0
    K D ·
    That’s right.
    You can login POINT and search for the error.
  6. 0
    Jorge Taguinod ·
    I’ve been having AVAA errors and reported these promptly to Primavera. According to them, these are just layout errors caused by low memory on your computer. So, there’s nothing to worry about since project data is not compromised.

    As for Primavera Support, I don’t find them reliable these days. Unlike during the P3 days where solutions were given within 24 hours, it now takes weeks for a problem to be properly addressed. Sometimes they even give out the wrong advice simply because they have not read through the problem provided by the user.

    Maybe Primavera should pay Planning Planet as I think that this forum provides more answers to users than Primavera itself. Imagine how much more tech support people Primavera should hire to support its users if Planning Planet were not around.

    Jorge
  7. 0
    K D ·
    Yes I agree with you.
    Sometimes I feel they feedback us without research our question.
    Very bad now.
    Regards
  8. 0
    David Forrest ·
    Many AVAAO errors are fixed in SP4, certainly reduced the number of incidents in our database, I also recommend that you purge/delete regularly.

Log in or join to reply